文章预览
Click on the top to follow us SIBUR is preparing to implement a project to reconstruct the pipeline that supplies ethylene from PJSC Nizhnekamskneftekhim to PJSC Kazanorgsintez. SIBUR intends to construct the new Nizhnekamsk-Kazan main ethylene pipeline with modern safety and oversight systems to replace the current ethylene pipeline built in 1976, with commissioning scheduled for 2026. "Stable transportation of ethylene will be required from Nizhnekamskneftekhim to Kazanorgsintez following the launch of SIBUR's EP-600 flagship project. The new 254 km-long ethylene pipeline should increase the pumping of ethylene approximately 2.5-fold to 500,000 metric tpy and ensure the loading of promising polyethylene production projects at Kazanorgsintez. The diameter of the ethylene pipeline will also increase in order to ensure reliable pumping of this volume," the petrochemical holding’s press service said. The ethylene pipeline will be laid along a new route, bypassing Kazan. Although the ro
………………………………